The Challenge
During final commissioning, the client identified a critical design omission: no containment tanks for oil carried by gas through compressor units. With equipment already installed and fabricated overseas, a fast, compliant solution was needed. The project was under pressure, operating in a live, high-compliance environment with tight timeframes and no margin for error.
Our Solution
We collaborated with site engineers to design and fabricate retrofit containment tanks rated for explosive atmospheres. We managed installation, built new footings, modified pipework and installed a vent line through roof level—all while maintaining compliance, site safety and documentation requirements. The scope required elevated work platforms and coordination across multiple trades.
The Outcome
We delivered the project to spec, under time pressure and site constraints. The client was impressed with our responsiveness, professionalism and technical capability. Our performance led to additional commissioning work and an ongoing project relationship—proof that when it matters, we deliver.