A worker in safety gear stands on a raised orange lift beside a large metal industrial building, with machinery and pipes nearby under a blue sky. A white Snorkel lift is also positioned in front of the structure.

Case Study Retrofit Installation – LNG Compressor Station

The Challenge

During final commissioning, the client identified a critical design omission: no containment tanks for oil carried by gas through compressor units. With equipment already installed and fabricated overseas, a fast, compliant solution was needed. The project was under pressure, operating in a live, high-compliance environment with tight timeframes and no margin for error.

Our Solution

We collaborated with site engineers to design and fabricate retrofit containment tanks rated for explosive atmospheres. We managed installation, built new footings, modified pipework and installed a vent line through roof level—all while maintaining compliance, site safety and documentation requirements. The scope required elevated work platforms and coordination across multiple trades.

The Outcome

We delivered the project to spec, under time pressure and site constraints. The client was impressed with our responsiveness, professionalism and technical capability. Our performance led to additional commissioning work and an ongoing project relationship—proof that when it matters, we deliver.